Safety Precautions: All work must be performed by a qualified electrician wearing appropriate arc-flash PPE. De-energize the load side of the transformer before performing any circuit modifications following LOTO (Lock-Out/Tag-Out) procedures.
- Identify the circuits contributing to the current draw that exceeds the transformer's kVA nameplate rating.
- Perform load shedding by transferring non-essential circuits to an alternative power source or a secondary transformer.
- If the total demand cannot be reduced, install a secondary transformer in parallel (if the units are identical and compatible) or replace the existing unit with one that has a higher kVA capacity.
- After re-energizing the system, use a calibrated clamp meter to measure the current on all three phases to ensure the new load is consistently below the transformer's nameplate rating.
- Monitor the transformer temperature over the next 24 hours to confirm that the temperature stabilizes and no longer exhibits a rising trend under constant operation.